Earthquake!

That was a weird experience … my first earthquake. 5.6 magnitude, centered 9 miles away, the whole hotel shook for about 15 seconds. At the Adobe building across the road, the lights must not be wired in very tightly, because lights were flashing on and off the whole time. OK, I guess it’s sort of like being on an airplane during turbulance.

New websites

Those of you who develop custom software for clients have probably been burned more than once by clients who are disappointed with what you thought was going to be the “final” version, and start demanding countless changes. You’ve probably built pretty good defenses against this: I’ve seen contrators ask their clients to sign every single page of the spec so that there can be no question that the client got exactly what they were promised.

It doesn’t help. The client is still unhappy. They knew what you were going to build, intellectually, but as soon as they saw it in real life, they started finding lots of problems:

Custom development is that murky world where a customer tells you what to build, and you say, “are you sure?” and they say yes, and you make an absolutely beautiful spec, and say, “is this what you want?” and they say yes, and you make them sign the spec in indelible ink, nay, blood, and they do, and then you build that thing they signed off on, promptly, precisely and exactly, and they see it and they are horrified and shocked, and you spend the rest of the week reading up on whether your E&O insurance is going to cover the legal fees for the lawsuit you’ve gotten yourself into or merely the settlement cost. Or, if you’re really lucky, the customer will smile wanly and put your code in a drawer and never use it again and never call you back.

(from Set Your Priorities)

That’s just how the world works. A spec can’t reveal everything. Clients can’t use the spec for their real work, and they’ll never notice just how many keystrokes it takes to do basic operations until you get, at least, a UI prototype working.

A good way to defend yourself against this is to deliver lots and lots of interim versions to the client: real, working interim versions, and get them using it so you can build feedback into future iterations. Rather than going off in a cave and building something for a year, only to find out that 9 months of that work is wasted, you show the client something every month, say, and get instant feedback and then you adjust directions if needed. That’s one thing that many people waving the “agile” flag are talking about. The first delivery should be the minimum thing that could possibly be useful.

This should not be seen as an excuse to write code without designing it, first. All code is going to be designed eventually. But if you try to design it first in a programming language, the designing process is vastly slower than if you were designing it with pencil and paper and descriptive paragraphs in the English language, so you’re wasting time.

Anyway. Where was I going with this? Oh yes. For the first time, I had the honor of being the “client” in that client/developer relationship, when we hired Happy Cog Studios to build our new website.

We gave them a relatively precise, unambiguous spec. Basically, we wanted the same website as we already had, only we wanted it to be prettier.

Here’s what our original website, designed by Dave Shea, looked like (click to enlarge:)

It was a great design, but several years old, and it felt dated.

Happy Cog gave us a couple of design options to use as starting points:

Or:

Both were quite good, I think, but had showstoppers. The first design put the most important paragraph in a spot where people were very likely to miss it. The second design required 1024 pixels. Even when people have 1024×768 (or larger) monitors, they don’t keep their browsers that wide. And about 30% of the people we asked hated the orange.

Which led us into several rounds of iteration by “a committee of tasteless slobs,” that committee being mostly me, and somehow we ended up with a design that just got worse and worse and worse the more we tweaked it. This is what we started to build:

That’s when I knew we had to start over, and when I suddenly knew what it felt like when you told the barber to give you an “en brosse” haircut because you thought you would look like Tom Cruise, and that’s not what happened.

Anyway, at that point I realized the design was suffering because it was trying to stuff a FogBugz identity (with the kiwi and the FogBugz logotype) into a Fog Creek website (with the Fog Creek wave logo). This both ate a lot of space at the top of the page, where real estate was scarce, and made the page a confusing bundle of links.

Fortunately, Happy Cog was very patient with us. We asked them to start fresh, with a new design concept and a new designer. Second, we decided that the FogBugz website doesn’t have to look anything like the Fog Creek website. It should be a showcase for FogBugz, with a tiny link to Fog Creek at the bottom. Happy Cog would design the FogBugz website. The Fog Creek website, which far fewer people ever visit, is about the company itself. It links to our products but doesn’t have to have the same graphic design. I designed that myself, with a very minimalist design that captured the essense of the company:


Larger picture | Go to fogcreek.com

My favorite part is the slideshow, with a set of pictures that captures life at Fog Creek perfectly. It’s plain, it’s minimalist, it reflects the company personality, and it harks back to the very first website design from when we started the company seven years ago:

Happy Cog assigned Dan Mall to the redesign of the FogBugz page. His first design was really good, and I knew that it would be better to just shut up and give him artistic license to do whatever he thought was best. I thought that we could try and meddle in his design, tweaking things left and right, and get another bad design-by-committee, or we could just tell him we trusted him and whatever he delivered would be exactly what went live.

Which it was.


Larger picture | Go to fogbugz.com

So that’s where we stand. Babak and I spent a week creating a video FogBugz demo for the site using my favorite screen-recording program, TechSmith Camtasia. The sound we could get in the office was just not good enough, so we rented studio time to record the soundtrack.

It took a lot of editing, but we got the video down to about 13 minutes. Probably too long for a web video, but what can ya do. And I already talk to fast.

Anyway, that’s the saga of the new websites. How do you like them?

Some feedback on EBS

Jeff Atwood: “It’s a tremendous credit to Joel Spolsky that he made this crucial feature the centerpiece of the new FogBugz. I’m not aware of any other software lifecycle tools that go to such great lengths to help you produce good estimates.”

Rafe Colburn: “We’re rolling out FogBugz 6.0 at work, and I’m finding that I actually like the time tracking. For one thing, it’s a tool for focus. When you kick off the timer on a task, you don’t want to jump around and multitask because it will just throw off the timer. The timer feature itself is pretty easy to use.”

Scott Rosenberg: “What’s most interesting about the new FogBugz is what Spolsky and his team are calling ‘Evidence Based Scheduling…’”

Reg Braithwaite: “I built a prototype that did the exact thing that FogBugz is doing quite some time ago. However, prototypes are not shipping products. FogBugz is a shipping product. My prototype was not. And that makes all the difference.”

Also: I wrote an earlier article describing Evidence-Based Scheduling, which was in Better Software Magazine last March.

Evidence Based Scheduling

Software developers don’t really like to make schedules. Usually, they try to get away without one. “It’ll be done when it’s done!” they say, expecting that such a brave, funny zinger will reduce their boss to a fit of giggles, and in the ensuing joviality, the schedule will be forgotten.

Most of the schedules you do see are halfhearted attempts. They’re stored on a file share somewhere and completely forgotten. When these teams ship, two years late, that weird guy with the file cabinet in his office brings the old printout to the post mortem, and everyone has a good laugh. “Hey look! We allowed two weeks for rewriting from scratch in Ruby!”

Hilarious! If you’re still in business.

You want to be spending your time on things that get the most bang for the buck. And you can’t figure out how much buck your bang is going to cost without knowing how long it’s going to take. When you have to decide between the “animated paperclip” feature and the “more financial functions” feature, you really need to know how much time each will take.

Why won’t developers make schedules? Two reasons. One: it’s a pain in the butt. Two: nobody believes the schedule is realistic. Why go to all the trouble of working on a schedule if it’s not going to be right?

Over the last year or so at Fog Creek we’ve been developing a system that’s so easy even our grouchiest developers are willing to go along with it. And as far as we can tell, it produces extremely reliable schedules. It’s called Evidence-Based Scheduling, or EBS. You gather evidence, mostly from historical timesheet data, that you feed back into your schedules. What you get is not just one ship date: you get a confidence distribution curve, showing the probability that you will ship on any given date. It looks like this:

The steeper the curve, the more confident you are that the ship date is real.

Here’s how you do it.

1) Break ‘er down

When I see a schedule measured in days, or even weeks, I know it’s not going to work. You have to break your schedule into very small tasks that can be measured in hours. Nothing longer than 16 hours.

This forces you to actually figure out what you are going to do. Write subroutine foo. Create this dialog box. Parse the Fizzbott file. Individual development tasks are easy to estimate, because you’ve written subroutines, created dialogs, and parsed files before.

If you are sloppy, and pick big three-week tasks (e.g., “Implement Ajax photo editor”), then you haven’t thought about what you are going to do. In detail. Step by step. And when you haven’t thought about what you’re going to do, you can’t know how long it will take.

Setting a 16-hour maximum forces you to design the damn feature. If you have a hand-wavy three week feature called “Ajax photo editor” without a detailed design, I’m sorry to be the one to break it to you but you are officially doomed. You never thought about the steps it’s going to take and you’re sure to be forgetting a lot of them.

2) Track elapsed time

It’s hard to get individual estimates exactly right. How do you account for interruptions, unpredictable bugs, status meetings, and the semiannual Windows Tithe Day when you have to reinstall everything from scratch on your main development box? Heck, even without all that stuff, how can you tell exactly how long it’s going to take to implement a given subroutine?

You can’t, really.

So, keep timesheets. Keep track of how long you spend working on each task. Then you can go back and see how long things took relative to the estimate. For each developer, you’ll be collecting data like this:

Each point on the chart is one completed task, with the estimate and actual times for that task. When you divide estimate by actual, you get velocity: how fast the task was done relative to estimate. Over time, for each developer, you’ll collect a history of velocities.

  • The mythical perfect estimator, who exists only in your imagination, always gets every estimate exactly right. So their velocity history is {1, 1, 1, 1, 1, …}
  • A typical bad estimator has velocities all over the map, for example {0.1, 0.5, 1.7, 0.2, 1.2, 0.9, 13.0}
  • Most estimators get the scale wrong but the relative estimates right. Everything takes longer than expected, because the estimate didn’t account for bug fixing, committee meetings, coffee breaks, and that crazy boss who interrupts all the time. This common estimator has very consistent velocities, but they’re below 1.0. For example, {0.6, 0.5, 0.6, 0.6, 0.5, 0.6, 0.7, 0.6}

As estimators gain more experience, their estimating skills improve. So throw away any velocities older than, say, six months.

If you have a new estimator on your team, who doesn’t have a track record, assume the worst: give them a fake history with a wide range of velocities, until they’ve finished a half-dozen real tasks.

3) Simulate the future

Rather than just adding up estimates to get a single ship date, which sounds right but gives you a profoundly wrong result, you’re going to use the Monte Carlo method to simulate many possible futures. In a Monte Carlo simulation, you can create 100 possible scenarios for the future. Each of these possible futures has 1% probability, so you can make a chart of the probability that you will ship by any given date.

While calculating each possible future for a given developer, you’re going divide each task’s estimate by a randomly-selected velocity from that developer’s historical velocities, which we’ve been gathering in step 2. Here’s one sample future:

Estimate: 4 8 2 8 16
Random Velocity: 0.6 0.5 0.6 0.6 0.5 Total:
E/V: 6.7 16 3.3 13.3 32 71.3

Do that 100 times; each total has 1% probability, and now you can figure out the probability that you will ship on any given date.

Now watch what happens:

  • In the case of the mythical perfect estimator, all velocities are 1. Dividing by a velocity which is always 1 has no effect. Thus, all rounds of the simulation give the same ship date, and that ship date has 100% probability. Just like in the fairy tales!
  • The bad estimator’s velocities are all over the map. 0.1 and 13.0 are just as likely. Each round of the simulation is going to produce a very different result, because when you divide by random velocities you get very different numbers each time. The probability distribution curve you get will be very shallow, showing an equal chance of shipping tomorrow or in the far future. That’s still useful information to get, by the way: it tells you that you shouldn’t have confidence in the predicted ship dates.
  • The common estimator has a lot of velocities that are pretty close to each other, for example, {0.6, 0.5, 0.6, 0.6, 0.5, 0.6, 0.7, 0.6}. When you divide by these velocities you increase the amount of time something takes, so in one iteration, an 8-hour task might 13 hours; in another it might take 15 hours. That compensates for the estimators perpetual optimism. And it compensates precisely, based exactly on this developers actual, proven, historical optimism. And since all the historical velocities are pretty close, hovering around 0.6, when you run each round of the simulation, you’ll get pretty similar numbers, so you’ll wind up with a narrow range of possible ship dates.

In each round of the Monte Carlo simulation, of course, you have to convert the hourly data to calendar data, which means you have to take into account each developer’s work schedule, vacations, holidays, etc. And then you have to see, for each round, which developer is finishing last, because that’s when the whole team will be done. These calculations are painstaking, but luckily, painstaking is what computers are good at.

Obsessive-compulsive disorder not required

What do you do about the boss who interrupts you all the time with long-winded stories about his fishing trips? Or the sales meetings you’re forced to go to even though you have no reason to be there? Coffee breaks? Spending half a day helping the new guy get his dev environment set up?

When Brett and I were developing this technique at Fog Creek, we worried a lot about things that take real time but can’t be predicted in advance. Sometimes, this all adds up to more time than writing code. Should you have estimates for this stuff too, and track it on a time sheet?

Well, yeah, you can, if you want. And Evidence Based Scheduling will work.

But you don’t have to.

It turns out that EBS works so well that all you have to do is keep the clock running on whatever task you were doing when the interruption occurred. As disconcerting as this may sound, EBS produces the best results when you do this.

Let me walk you through a quick example. To make this example as simple as possible, I’m going to imagine a very predictable programmer, John, whose whole job is writing those one-line getter and setter functions that inferior programming languages require. All day long this is all he does:

private int width;
public int getWidth () { return width; }
public void setWidth (int _width} { width = _width; }

I know, I know… it’s a deliberately dumb example, but you know you’ve met someone like this.

Anyway. Each getter or setter takes him 2 hours. So his task estimates look like this:

{2, 2, 2, 2, 2, 2, 2, 2, 2, 2, 2, … }

Now, this poor guy has a boss who interrupts him every once in a while with a two-hour conversation about marlin fishing. Now, of course, John could have a task on his schedule called “Painful conversations about marlin,” and put that on his timesheet, but this might not be politically prudent. Instead, John just keeps the clock running. So his actual times look like this:

{2, 2, 2, 2, 4, 2, 2, 2, 2, 4, 2, … }

And his velocities are:

{1, 1, 1, 1, 0.5, 1, 1, 1, 1, 0.5, 1, … }

Now think about what happens. In the Monte Carlo simulation, the probability that each estimate will be divided by 0.5 is exactly the same as the probability that John’s boss would interrupt him during any given feature. So EBS produces a correct schedule!

In fact, EBS is far more likely to have accurate evidence about these interruptions than even the most timesheet-obsessive developer. Which is exactly why it works so well. Here’s how I explain this to people. When developers get interrupted, they can either

  1. make a big stink about putting the interruption on their timesheet and in their estimates, so management can see just how much time is being wasted on fishing conversation, or
  2. make a big stink about refusing to put it on their timesheet, just letting the feature they were working on slip, because they refuse to pad their estimates which were perfectly correct with stupid conversation about fishing expeditions to which they weren’t even invited,

… and in either case, EBS gives the same, exactly correct results, no matter which type of passive-aggressive developer you have.

4) Manage your projects actively

Once you’ve got this set up, you can actively manage projects to ship on time. For example, if you sort features out into different priorities, it’s easy to see how much it would help the schedule if you could cut the lower priority features.

You can also look at the distribution of possible ship dates for each developer:

Some developers (like Milton in this picture) may be causing problems because their ship dates are so uncertain: they need to work on learning to estimate better. Other developers (like Jane) have very precise ship dates that are just too late: they need to have some of their work taken off their plate. Other developers (me! yay!) are not on the critical path at all, and can be left in peace.

Scope creep

Assuming you had everything planned down to the last detail when you started work, EBS works great. To be honest, though, you may do some features that you hadn’t planned. You get new ideas, your salespeople sell features you don’t have, and somebody on the board of directors comes up with a cool new idea to make your golf cart GPS application monitor EKGs while golfers are buzzing around the golf course. All this leads to delays that could not have been predicted when you did the original schedule.

Ideally, you have a bunch of buffer for this. In fact, go ahead and build buffer into your original schedule for:

  1. New feature ideas
  2. Responding to the competition
  3. Integration (getting everyone’s code to work together when it’s merged)
  4. Debugging time
  5. Usability testing (and incorporating the results of those tests into the product).
  6. Beta tests

So now, when new features come up, you can slice off a piece of the appropriate buffer and use it for the new feature.

What happens if you’re still adding features and you’ve run out of buffer? Well, now the ship dates you get out of EBS start slipping. You should take a snapshot of the ship date confidence distribution every night, so that you can track this over time:

The x-axis is when the calculation was done; the y-axis is the ship date. There are three curves here: the top one is the 95% probability date, the middle is 50% and the bottom is 5%. So, the closer the curves are to one another, the narrower the range of possible ship dates.

If you see ship date getting later and later (rising curves), you’re in trouble. If it’s getting later by more than one day per day, you’re adding work faster than you’re completing work, and you’ll never be done. You can also look and see if the ship date confidence distribution is getting tighter (the curves are converging), which it should be if you’re really converging on a date.

While we’re at it

Here are a few more things I’ve learned over the years about schedules.

1) Only the programmer doing the work can create the estimate. Any system where management writes a schedule and hands it off to programmers is doomed to fail. Only the programmer who is going to implement a feature can figure out what steps they will need to take to implement that feature.

2) Fix bugs as you find them, and charge the time back to the original task. You can’t schedule a single bug fix in advance, because you don’t know what bugs you’re going to have. When bugs are found in new code, charge the time to the original task that you implemented incorrectly. This will help EBS predict the time it takes to get fully debugged code, not just working code.

3) Don’t let managers badger developers into shorter estimates. Many rookie software managers think that they can “motivate” their programmers to work faster by giving them nice, “tight” (unrealistically short) schedules. I think this kind of motivation is brain-dead. When I’m behind schedule, I feel doomed and depressed and unmotivated. When I’m working ahead of schedule, I’m cheerful and productive. The schedule is not the place to play psychological games.

Why do managers try this?

When the project begins, the technical managers go off, meet with the business people, and come up with a list of features they think would take about three months, but which would really take twelve. When you think of writing code without thinking about all the steps you have to take, it always seems like it will take n time, when in reality it will probably take more like 4n time. When you do a real schedule, you add up all the tasks and realize that the project is going to take much longer than originally thought. The business people are unhappy.

Inept managers try to address this by figuring out how to get people to work faster. This is not very realistic. You might be able to hire more people, but they need to get up to speed and will probably be working at 50% efficiency for several months (and dragging down the efficiency of the people who have to mentor them).

You might be able to get 10% more raw code out of people temporarily at the cost of having them burn out 100% in a year. Not a big gain, and it’s a bit like eating your seed corn. Of course, when you overwork people, debugging time doubles and a late project becomes later. Splendid karma.

But you can never get 4n from n, ever, and if you think you can, please email me the stock symbol for your company so I can short it.

4) A schedule is a box of wood blocks. If you have a bunch of wood blocks, and you can’t fit them into a box, you have two choices: get a bigger box, or remove some blocks. If you wanted to ship in six months, but you have twelve months on the schedule, you are either going to have to delay shipping, or find some features to delete. You just can’t shrink the blocks, and if you pretend you can, then you are merely depriving yourself of a useful opportunity to actually see into the future by lying to yourself about what you see there.

Now that I mention it, one of the great benefits of realistic schedules is that you are forced to delete features. Why is this good?

Suppose you have two features in mind. One is really useful and will make your product really great. The other is really easy and the programmers can’t wait to code it up (”Look! <blink>!”), but it serves no useful purpose.

If you don’t make a schedule, the programmers will do the easy/fun feature first. Then they’ll run out of time, and you will have no choice but to slip the schedule to do the useful/important feature.

If you do make a schedule, even before you start working, you’ll realize that you have to cut something, so you’ll cut the easy/fun feature and just do the useful/important feature. By forcing yourself to chose some features to cut, you wind up making a more powerful, better product with a better mix of good features that ships sooner.

Way back when I was working on Excel 5, our initial feature list was huge and would have gone way over schedule. “Oh my!” we thought. “Those are all super important features! How can we live without a macro editing wizard?”

As it turns out, we had no choice, and we cut what we thought was “to the bone” to make the schedule. Everybody felt unhappy about the cuts. To make people feel better, we told ourselves that we weren’t cutting the features, we were simply deferring them to Excel 6.

As Excel 5 was nearing completion, I started working on the Excel 6 spec with a colleague, Eric Michelman. We sat down to go through the list of “Excel 6” features that had been punted from the Excel 5 schedule. Guess what? It was the shoddiest list of features you could imagine. Not one of those features was worth doing. I don’t think a single one of them ever was. The process of culling features to fit a schedule was the best thing we could have done. If we hadn’t done this, Excel 5 would have taken twice as long and included 50% useless crap features that would have had to be supported, for backwards compatibility, until the end of time.

Summary

Using Evidence-Based Scheduling is pretty easy: it will take you a day or two at the beginning of every iteration to produce detailed estimates, and it’ll take a few seconds every day to record when you start working on a new task on a timesheet. The benefits, though, are huge: realistic schedules.

Realistic schedules are the key to creating good software. It forces you to do the best features first and allows you to make the right decisions about what to build. Which makes your product better, your boss happier, delights your customers, and—best of all—lets you go home at five o’clock.

P.S.

Evidence Based Scheduling is built into FogBugz 6.0.

Five easy ways to fail

“Even though a bad team of developers tends to be the No. 1 cause of software project failures, you’d never know it from reading official postmortems. In all fields, from software to logistics to customer service, people are too nice to talk about their co-workers’ lack of competence. You’ll never hear anyone say ‘the team was just not smart enough or talented enough to pull this off.’ Why hurt their feelings? The simple fact is that if the people on a given project team aren’t very good at what they do, they’re going to come into work every day and yet—behold!—the software won’t get created.”

Five Easy Ways to Fail, from the November Inc. Magazine.

The Institute for Kiwi Studies

Oh yes. It turns out the Māori translation we were using for the translation of the fictional Institute for Kiwi Studies had a slight grammatical error; thanks to Professor Ray Harlow of the University of Waikato, who wrote the most up-to-date Māori language grammar, it should be “Te Tari Mātauranga o te Tokoeka,” and indeed, it is concerned with the study of the South Island kiwi, Apteryx australis.

Kiwis feed on worms, berries, insects, leaves, reptiles, and amphibians. They locate their food by scratching through the dead leaves with their claws or by probing the ground with their bill.

Kiwi!

FogBugz World Tour video now available

Here’s a video (70 minutes, Flash) of the demo I gave of FogBugz in Austin, Texas last week.

A few technical details for the geeks:

The demo itself was broadcast live from the Hyatt Regency in Austin by the crew from NewTek, who came for the opportunity to play around with their TriCaster, which is, essentially, a broadcast studio in a backpack-sized box. Well, OK, not quite a backpack: they brought a couple of crates with remote control video cameras, mics, cables, and a big LCD screen for controlling everything. It took them about half an hour to completely set up. Aussie Holten from NewTek ran the production live, which was fed over the Internet. I think we had something on the order of 150 live viewers at the time.

The final video, compressed in Flash Video format, came out to about 264 MB, so the next trick was finding a place to host it.

We’ve always been happy with Peer 1 Network, which was kind enough to offered to host Joel on Software for free back in the old days, but which has proven to be an excellent colocation provider and an excellent tier 1 provider.

(Fog Creek is now using two racks, one in LA and one in New York, and quite a bit of bandwidth, which we’re paying for.)

So anyway, when we needed a place to host the video, I naturally asked Peer 1, and it turns out they have something called a Content Delivery Network. The idea is that your huge files are spread out on servers in 17 different cities, and everybody downloads it from whichever one is closest. They got the whole thing set up in a matter of hours.

So, let’s try it out!

Eurotour

Next up on the FogBugz World Tour: Europe!

(Map thanks to Paul Demers and Google).

Registration is now open for November:

Nov 7: Dublin
Nov 8: Cambridge
Nov 9: London
Nov 12: Amsterdam
Nov 13: Copenhagen

The morning of November 14th, I’ll be speaking at Øredev, a conference for software developers in Malmö, Sweden… this keynote speech is called “Developing Great Software” and is not a FogBugz demo.

PS. I’m kind of new to this video thing. The Austin FogBugz demo turned out to be a 256MB flash video (FLV), and I think we really need a streaming Flash server to host it, which we don’t have. I think this is the point of content delivery networks. If you have an idea for someplace I can quickly put an FLV for streaming to large numbers of people, please let me know.

Introducing FogBugz 6.0

At some point, while I was running around the country giving demos of FogBugz 6.0, the development team officially got it out the door, and I don’t think I ever officially announced, “FogBugz 6.0 is now shipping,” so, here it is:

FogBugz 6.0 is now shipping!

It has a ton of major new features: an integrated Wiki, an API, a completely overhauled search engine, and lots of Ajax to make things really snappy.

Probably the most interesting part of 6.0 is Evidence-Based Scheduling, which uses a statistical technique called bootstrapping (a variation on Monte Carlo) to determine the probability that you’ll ship on any given date. EBS is interesting enough that I’ll devote a whole article to explaining it as soon as I get a minute of free time. Briefly, with EBS, you estimate features as usual. But then, instead of adding up everyone’s estimates—instead of taking them on faith—FogBugz does a Monte Carlo simulation looking at what speeds developers worked at in the past, vis-à-vis their estimates. You use that same distribution of probabilities that you had in the past and run a simulation of 60 futures each of which will occur with equal probability. What you get, instead of a date, is a probability distribution curve that shows the probability that the product will ship on such-and-such a date:

The introductory price is a terrific deal, and it’s only good until November 1st. For example, a ten-pack is only $999 instead of $1899. If you sign up for the On Demand version, you can lock in a rate of $21/user/month instead of $25. Go make yourself a free online trial, what are you waiting for?